− | + | Bootstrapping our way to the Moon | |
+ | |||
+ | == Stage 1: == | ||
+ | |||
Week Long Team meeting $20,000 | Week Long Team meeting $20,000 | ||
− | Preliminary visit with JPL or [http://idc.nasa.gov/ Goddard | + | |
+ | Preliminary visit with [http://jplteamx.jpl.nasa.gov/ JPL TeamX] or [http://idc.nasa.gov/mdl Goddard Mission Design Center] $100,000 | ||
+ | |||
+ | == Stage 2: == | ||
+ | |||
Week Long Team Meeting $20,000 | Week Long Team Meeting $20,000 | ||
+ | |||
end-to-end mission design visit with JPL/Goddard $300,000 | end-to-end mission design visit with JPL/Goddard $300,000 | ||
− | == | + | == Stage 3: == |
− | + | Based on results of Stage 2, namely the details of the end-to-end mission design | |
− | + |
Latest revision as of 20:23, 11 October 2008
Bootstrapping our way to the Moon
[edit] Stage 1:
Week Long Team meeting $20,000
Preliminary visit with JPL TeamX or Goddard Mission Design Center $100,000
[edit] Stage 2:
Week Long Team Meeting $20,000
end-to-end mission design visit with JPL/Goddard $300,000
[edit] Stage 3:
Based on results of Stage 2, namely the details of the end-to-end mission design